When creating or editing a booking, the service field shows a badge with the hours left to schedule on the selected service.
The badge updates after saving, reflecting the impact of your booking.
How the Calculation Works
The badge value depends on the Show remaining hours as setting configured by your admin in Settings > Resourcing > Planning & scheduling.
Unscheduled time
Calculated as: Estimate − Total scheduled
Choose this if your team plans work upfront and schedules everything before it's worked. It gives you a clear picture of how much has been booked versus what's still open, without factoring in logged time.
Unaccounted time
Calculated as: Estimate − (Worked + Future scheduled)
Choose this if your team logs time as work progresses. It subtracts both past work and future bookings, so the badge reflects what genuinely still needs to be planned.
📌 Today counts as a future date in both calculations.
Reading the Badge
The badge color tells you where the service stands:
🟢 Green — hours remain (e.g. 50 hrs)
⚪️ Gray/neutral — fully scheduled, nothing left
🔴 Red — over-scheduled (e.g. −12 hrs)
The badge updates after each save, so you can track remaining hours as your schedule evolves.
📌 Example (Unaccounted time): A service has a 10-hour estimate. 0 hours have been worked, and 9 hours are in future bookings. The badge shows 1 hr remaining as unaccounted time.
📌 Example (Unscheduled time): A service has a 10-hour estimate. 10 hours are scheduled across bookings. The badge shows 0 hrs of unscheduled time.